300 Harrow Road

The 300 Harrow Road scheme completed in winter 2023. 77 homes are designated for social rent and 35 at London Living Rent levels, making this scheme 100% affordable homes for the community.

The scheme also benefits from improved landscaping at its centre. A new canal-side landscape area improves connectivity between Harrow Road and the canal ensuring people can enjoy this important local amenity.

A local lettings plan has enabled those nearby households on our housing waiting list to move into a new council home at the development.

Timeline

  • May 2020: planning committee approval
  • December 2020: site preparation works begin
  • January 2021: Harrow Road nursery opens at temporary site
  • Summer 2021: construction begins at 300 Harrow Road
  • July 2021: cranes brought on site
  • May 2022: tallest point of buildings complete
  • Winter 2023: construction finishes
  • Winter 2023/2024: residents move into new homes

Have a question?

If you have a question about the works at 300 Harrow Road, please fill out our contact form or email us at [email protected]. A member of the team will be in touch as soon as possible