Current status
Project status
1
Initial planning
Deciding the scope of the works
Project status
2
Project design and approval
Finalising the project specification, budget and programme
Project status
3
Project status
4
Completion
End of works and the defects period
Project outline
The following works are currently in progress on the Avenue Gardens Estate:
- Full roof renewal.
- Drainage and guttering repairs.
- External repairs and decorations.
Please note that some of the work planned for Birch House was brought forward, and is now complete. The latest update on Birch House is here.
The site set up started in mid-July, with the first scaffold starting from 15 August 2022. Works are scheduled to complete to all blocks by November 2024.
More details can be found under the Project Update page.
For more information about the project contact us, quoting major works reference W103.
Published: 21 January 2021
Last updated: 17 October 2024