Skip to main content

Hall and Braithwaite Towers Communal Ventilation and Fire Safety Works (project X254)

Current status

Project status 1
Initial planning

Deciding the scope of the works

Project status 2
Project design and approval

Finalising the project specification, budget and programme
 

Project status 3
Onsite
Work starts: 16/01/2025
Work ends: 17/11/2025
Project status 4
Completion

End of work and the defects process

Project update

Our contractor, Axis, is working on the detailed plans and costs for the works to your home. A copy of the most recent update is under the Documents Tab. 

As outlined in the update, we are arranging the pilot works in advance of the works starting.

Our contractor Axis is working on the different design options of the proposed communal doors, flat entrance door sets and in flat ventilation. 

 

Published: 25 March 2021

Last updated: 17 October 2024