Current status
Deciding the scope of the works
Finalising the project specification, budget and programme
End of works and the defects period
Project update
Work to the Lanark Road street properties is underway. There has been a variation in the scope of the work to these properties. We will include roof renewal work and fit extra insulation. We are doing this work because the existing roofs were approaching the end of their lifespan.
Our Commissioning Team is continuing to undertake a thorough review of the proposal of works and costings. This often takes place to ensure that they meet the requirements of the Client Brief and represent value for money for residents and the Council alike. Note this work is very detailed and takes a considerable amount of time.
When our checks, and any associated queries have been completed we will have a more clearly defined scope of works. At this point we will contact you again to share this information with you and get your feedback.
December 2024 Update
Our contractors Axis are currently arranging surveys to be undertaken to the external facades of each block. The surveys will require drilling into the façade, to take samples for lab testing.
The work will start week beginning 9 December 2024 and will be completed by Tuesday 17 December 2024.
Axis will not require access into your homes, as these works will be done externally.
Axis representatives have hand delivered letters to all blocks regarding the surveys.
Thank you for your co-operation.
Published: 26 March 2021
Last updated: 3 December 2024