Wharncliffe Gardens Repairs and Decorations (project AC103)

Current status

Project status 1
Initial planning

Deciding the scope of the works

Project status 2
Project design and approval

Finalising the project specification, budget and programme

Project status 3
Onsite
Work starts: 28/02/2022
Work ends: 31/10/2024
Project status 4
Completion

End of work defects

Project update

End of project is near

The major works project is largely complete and we are very grateful for your patience. 

The team at Westminster Council and United Living would also like to thank resident working party who have been very effective at raising the residents' priorities during the delivery of these works. They have given up their time for free. 

Invites were sent to all resident for the block inspections which took place on Wednesday 29 and Thursday 30 May. A record of the issues noted has been shared with the Working Party. Please let us know if you would like a copy.  

The team from United Living is working through the list of 'snagging' from the walkabouts and other inspections, after which the project will complete and move into the 'defects period'. 

This snagging related work is almost complete and the project is due to finish up at the end of October. 

As we move into the defects periods, we will send you an 'Aftercare booklet' with information that will help you to look after any new items that we have fitted. 

If you have any questions about the project, please contact Henrietta, your Resident Liaison Officer, on 07802 666 972 or email [email protected].

Published: 20 January 2021

Last updated: 17 October 2024